High-voltage pylon and a small substation in open farmland at blue hour

Powerfirst.

We develop data-center sites of 20 to 100 MW in Germany on former power plant and industrial land with existing grid infrastructure. There, power is available sooner than through a new grid connection.

For owners

  • A value-adding use for land and grid infrastructure
  • At no cost to you
  • Discreet, in clearly agreed steps

The bottleneck is not demand. It is the grid connection.

Since April 2026, new connections to the transmission grid have been allocated by project maturity, no longer by date of application. Whoever brings together suitable land, a sound concept and a strong applicant gets connected sooner.

Row of high-voltage pylons in morning mist over frosted fields
Illustrative image: overhead power line in morning mist.
  • 4×

    The federal government aims to quadruple AI data-center capacity in Germany by 2030 compared with 2025.

  • 720 GW

    Grid connection capacity requested for large battery storage alone; about 78 GW has been confirmed.

  • 2030s

    In many congested regions, new large loads will not be connected before the next decade.

Sources: German Federal Government, “Deutschland als KI-Nation 2030” (Nov 2026); BDEW, grid connection requests for large battery storage (Nov 2025); Mainova on new connections in Frankfurt (2026); transmission grid operators on the maturity-based procedure (2026).

What we do

Blueacre finds sites with existing grid infrastructure: power plants and industrial plants facing closure, land next to substations with spare capacity. We secure the land together with the owner, prepare a complete, verifiable grid application for power supply in line with the grid operators’ maturity criteria, and hand over the project company with its grid reservation to an operator who builds.

  • Find

    We analyse registers, grid data and site information across Germany and identify suitable land early.

  • Develop

    Land, permitting roadmap, technical concept and applicant: brought together in a mature, clearly structured grid application.

  • Hand over

    Sale or partnership at agreed milestones, with a clean, auditable project file.

Aerial view of a vacant, well-kept industrial site with halls, a yard, a rail siding and a fenced transformer station
Illustrative image: former industrial site with rail access and a transformer station.

How we work

  1. 1. Initial assessment

    We assess your land: grid, planning, heat, realistic size.

  2. 2. Agreement

    Exclusive cooperation for a fixed period, at no cost to you.

  3. 3. Grid application

    Application for power supply with a complete maturity file.

  4. 4. Municipality

    Early, open coordination with the municipality and district, including a waste-heat concept.

  5. 5. Handover

    Sale or stake to an operator at agreed milestones.

Single-line diagram of a substation and a site plan, with a scale ruler, pencil and notebook
Illustrative image: single-line diagram and site plan.

Who we work with

  • Owners and administrators

    A value-adding use for land and grid infrastructure, at no cost to you. We work discreetly and in clearly agreed steps.

  • Municipalities and economic development

    Existing sites before new build, where possible without sealing new land, waste heat for the district heating network, business tax and jobs, open coordination from the start.

  • Operators and investors

    Sites of 20 to 100 MW with a demonstrable path to a grid connection, at a scale that large platforms do not cover.

Aerial view of a data-center campus in morning light: two long halls with dry coolers on the roofs, an office building, a row of backup generators and a substation
Illustrative image: data-center campus with backup generators and a substation.

Initial assessment

Do you own or manage industrial, power plant or commercial land? We check whether it is suitable for a data center: grid situation, responsible grid operator and allocation procedure, planning status, waste heat, realistic scale. You receive a written assessment.

Non-binding, confidential and at no cost to you.

Substation seen straight from above, with transformers, gantries and a control building, surrounded by fields

Principles

  • Existing sites before new build: we develop previously used land, where possible without sealing new land.
  • Waste heat is planned in from the start.
  • No grid applications without a concrete project and partner.
  • Open with the municipality and the grid operator from the first enquiry.

About Blueacre

Blueacre combines nationwide site analysis, detailed knowledge of grid connection procedures and experience with transactions. Our aim: to put land with existing grid infrastructure to the use that creates the greatest value: for owners, municipalities and operators.